Republic of the Philippines
SUPREME COURT
Manila

EN BANC

G.R. Nos. L-14948 and L-14972            October 31, 1961

COMMERCIAL UNION ASSURANCE CO., LTD., plaintiff-appellee,
vs.
MANILA PORT SERVICE, ET AL., defendants-appellants.

Ozaeta, Gibbs and Ozaeta for plaintiff-appellee.
D. F. Macarañas for defendant-appellant Manila Port Service.
Rodolfo G. Flores for all other defendants-appellants.

PAREDES, J.:

Upon stipulation of facts, the Court of First Instance of Manila, rendered judgment "sentencing the defendants to pay the plaintiff the sum of P745.95 plus 15% thereof as and for attorney's fees and costs." Plaintiff appealed from the decision, insofar as it failed to award interest at the legal rate upon the principal sum of P745.95, from be date of the filing of the complaint; attorney's fees in the sum of P300.00 and liquidated damages and costs in an amount equal to 15% of said P745.95. The defendants likewise appealed on a question of law.

P. J. Rhodes & Co., as shipper, placed on board 'M.S. Tosima' at New Orleans, a shipment of 4,000 bags of soybean meal, consigned to the same company for which the owner of the shipping company issued a bill of lading No 5, which was endorsed by the consignee to San Miguel Brewery, Manila, on May 7, 1956. Of the 4,000 bags, defendant Manila Port Service, a subsidiary of the defendant Manila Railroad Co., Inc. failed to deliver to San Miguel Brewery 26 bags. Upon demand by San Miguel Brewery, the herein plaintiff, Commercial Union Assurance Company, Ltd., as insurer of the goods, paid the former the sum of P745.95, and thereafter the plaintiff became subrogated to all the rights of the insured. This action was brought by the insurer to collect from the arrastre operators (defendants) the value of the 26 bags which were lost.

In the answer presented by the defendant, as well as in the stipulation of facts, the main defense is that the plaintiff's claim was not filed within the fifteen-day period from date of the discharge of the last package at the Port of Manila, in violation of section 15 of the management contract between the Manila Port Service and the Bureau of Customs dated February 29, 1956, which, according to the defendants, is binding upon the plaintiff. The plaintiff contends otherwise.

From the stipulation of facts, it appears that "the last bag of the shipment was discharged from the carrying vessel on May 9, 1956, whereas the provisional claim was filed on May 25, 1956," or one day late.

In its appeal, the plaintiff alleged that the trial court erred in failing to award it legal interest on the principal sum of P745.95, from February 19, 1959, the date of judicial demand and in failing to award attorney's fees in full P300.00. In their appeal, the defendants averred that the lower court erred in not holding the management contract binding upon the plaintiff-appellee; in including in the decision the sum of P308.16, representing the marked-up value of the 26 bags of soybean meal, when the same had not been admitted by defendants-appellants in the stipulation of facts and in ordering them to pay damages.

The pertinent portion of section 15 of the management contract under consideration provides: —

... in any event the CONTRACTOR shall be relieved and released of any and all responsibility or liability for loss, damage, misdelivery, and/or non-delivery of goods unless suit in the court of proper jurisdiction is brought within a period of one (1) year from the date of the discharge of the goods, or from the date when the claim for the value of such goods have been rejected or denied by the CONTRACTOR, provided that such claim shall have been filed with the CONTRACTOR within fifteen (15) days from the date of discharge of the last package from the carrying vessel.

At the time the goods were discharged, the above quoted section 15 was stamped on the delivery permit and on the gate pass; the consignee signed the delivery permit and the corresponding gate pass, which signified acceptance of the said provision of the management contract. Of course, the trial court, and with it the plaintiff-appellant contended that said acts did not constitute acceptance of or acquiescence to the provisions of the management contract, but they merely showed that the consignee, not being a party to the management contract, the latter cannot reach or affect it; and that Article 1311 of the Civil Code is not applicable, because the management contract does not contain provisions which are in the nature of stipulation " pour autui".

When the original briefs of the parties in this case were submitted, there was really much room for indulging in legal disquisitions on the dominant question involved therein. Since then, however, this tribunal had blazed the trail to pursue. Thus, in the case of Domestic Insurance Co. of the Philippines vs. Manila Port Service, et al., L-15060, Aug. 31, 1960, We said: —

In previous cases ... already decided by this Court, we held that where the third party is duly notified, and acts with knowledge of the provisions of the Management Contract, such party would be bound by the Contract. In the case of Tomas Grocery v. Delgado Brothers, Inc., L-11154, April 29, 1959, we likewise held that under the fact therein found, the 15-day period provision was binding. In other words, it cannot be said that the Management Contract is, or is not binding on third parties, without regard to the facts of each particular case. And since the appealed decision now before us, does not contain enough findings of fact upon which to resolve with justice the rights of the parties hereto, we decide to give them further opportunity to fully prove their respective contentions.

In the case of Villanueva vs. Barber-Wilhelmsem Line, et al., No. L-14764, Nov. 30, 1960, We stated: —

... The question whether the abovequoted paragraph of the management contract is binding to a consignee, who, though not a party thereto, has taken delivery of the goods upon presentation of a pass and a delivery permit making reference to said paragraph and reproducing substantially the provisions thereof, as one of the conditions of said pass and delivery permit, has already been settled in several decisions of this Court. On Northern Motors, Inc. vs. Prince Line, L-13884, Feb. 29, 1960, we said:

Even thereof, if appellant was not a signatory to said management contract, it legally became a party thereto when through its broker, the Luzon Brokerage Co., Inc. obtained the delivery permit and gate pass in the above manner prescribed by law and, making use of them, demanded from appellee the delivery of the 33 cases, pursuant to appellee's undertaking in virtue of the very same Management Contract. Again, it became bound when it brought court action against appellee, also by virtue of the latter's obligations as the arrastre contractor under the same Management Contact, for the purpose of recovering the reasonable value of the missing case of auto spare parts and accessories.

This view was reiterated in Tomas Grocery vs. Delgado Brothers, L-11154, April 29, 1959; Bernabe vs. Delgado Brothers, L-14360, Feb. 29, 1960; Bernabe vs. Delgado Brothers, L-12058, April 27, 1960; Delgado Brothers vs. Li Yao & Co., L-12872, April 29, 1960; Sun Brothers vs. Manila Port Service, L-13500, April 29, 1960; and Juan Ysmael & Co., Inc. vs United States Lines Co., L-14394, April 30, 1960.

Being a settled issue, that a management contract has a binding effect on the consignee who takes advantage thereof, even though he is not a party thereto, the next question posed is whether or not the management contract under consideration has been complied with. Plaintiff-appellant explained in its reply memorandum that although the cargo was discharged on May 9, 1956, from the carrying vessel, it was only on May 25, 1956 that defendants delivered them to the consignee; so that, according to said plaintiff-appellant, the corresponding claim for the missing bags could not have been made before May 25, 1956, inasmuch as the consignee could not have known how many bags of the shipment in question were actually missing until after the delivery of the last bag had been made. But the management contract in question provided: "Within fifteen (15) days from the date of the discharge of the last package from the carrying vessel", and not 15 days from the receipt of the last bag by the consignee, and the stipulation of facts stated that "the last bag of the shipment in question was discharged from the carrying vessel at the Port of Manila on May 9, 1956, whereas provisional claim was filed by the consignee on May 25, 1956, which is beyond the 15-day period" — on day late.

IN VIEW OF THE ABOVE CONCLUSION, we deem it unnecessary to pass upon the other issues raised by both parties. The decision appealed from, therefore, is reversed and another entered dismissing the complaint, with costs against the plaintiff-appellant.

Bengzon, C.J., Padilla, Bautista Angelo, Labrador, Concepcion, Reyes, J.B.L., and De Leon, JJ., concur.
Barrera and Dizon, JJ., took no part.


The Lawphil Project - Arellano Law Foundation